Indicative 0-40%
Provisional 41-70%
Committed 71-100%
NOW
NEXT
LATER
26 MAR 2026
Target
Confidence
Status

All Initiatives

NOW
BI/AI Reporting Dashboard
100% Committed
Dietloff, Adi - UAT → Pilot
UAT → Pilot
Pilot is going well, getting more data as we now have 31 venues in the pilot. Some bug fixes and updates have been made based on feedback.
Reservations API – Signature Group MVP
100% Committed
GG - Feb 13, 2026
QA Complete
Completed - MVP rolled out for Signature Group. In testing with Dev. Will be tested when QA is available.
Stage 1 – Adyen / ValPay
90% Committed
Hina - Mar 18, 2026
In Delivery
In Delivery - completing tech debt component before parking ValPay build. Estimated completion 10 Apr.
Floor Plan & Mobile – Native App MVP
85% Committed
Philip, Luwan, Jim - ⚠️ May 8, 2026
In DeliveryHard Deadline
Milestone 4 complete and about to go to QA
Streamline Envs & Dev Cycle Process
100% Committed
Josh - Overdue
Done
Work completed and last little bit with QA
Hangfire → Message Queue
100% Committed
Simon - TBD
QA
QA resource dependent. Released next week behind a feature flag. Will go live week after Easter
US Infra & Environments Runbook
100% Committed
Julien, Faisal, Josh - ASAP
QABLOCKER
Complete but QA and Infra doing back and forth and making performance tweaks
Localisation – Timestamps AUD→US
70% Provisional
Van, Adi - May 2026
In DeliveryBlocked
FE and BE are working through tickets. BE is a little more work than the FE side
Square SDK Security – Digital Signature
100% Committed
Jack, Diet, FE-TBC - Apr–Jun 2026
QABlocked
Completed - with QA.
Gift Card UI/UX + No Expiry (USA/CA)
90% Committed
Yunfang, FE team - May 2026
In Delivery
Dev completion due 27 Mar. Priority 1 = No expiry for USA/CA. Priority 2 = UI/UX widget redesign.
CRM/EDM Integration – iframe partner
100% Committed
TBC - May 2026
Done
Done - P1 subscription button in admin complete. P2 (NBI domain) and P3 (SSO) post-launch.
Google Book Now Integration
70% Provisional
Simon - May 2026 (conditional)
In Delivery
Merchant Feed ~ready 13 Mar. Service Feed ~ready 20 Mar. Availability Feed ~ready 8 Apr (most complex). Booking Service and RTUs from 9 Apr, aiming to finish 24 Apr. Slow feedback cycle (24hr+ per test).
NEXT
LATER
CA/USA – Server by Section
TBD
Philip, Luwan, BE-TBC - Apr–Jun 2026
Parking Lot
Widget Redesigns – UI/UX
TBD
Philip, Luwan, Yunfang - Jul–Sep 2026
Parking Lot
Max Cover Limits per Service
TBD
Van, FE-TBC - Jul–Sep 2026
Parking Lot
IPOS Microservice Stage 2 – POS API
TBD
Jack, Diet, API hire - Jul–Sep 2026
Parking Lot
Kounta – K Series
TBD
New API Hire - Jul–Sep 2026
Parking Lot
Dynamic Seating
TBD
TBC - Oct–Dec 2026
Parking Lot

Release - Q1/Q2 2026

BI/AI Reporting Dashboard
Dietloff, Adi - UAT → Pilot
100% Committed - UAT → Pilot
Pilot is going well, getting more data as we now have 31 venues in the pilot. Some bug fixes and updates have been made based on feedback.
Reservations API – Signature Group MVP
GG - Feb 13, 2026
100% Committed - QA Complete
Completed - MVP rolled out for Signature Group. In testing with Dev. Will be tested when QA is available.
Stage 1 – Adyen / ValPay
Hina - Mar 18, 2026
90% Committed - In Delivery
In Delivery - completing tech debt component before parking ValPay build. Estimated completion 10 Apr.
Floor Plan & Mobile – Native App MVP
Philip, Luwan, Jim - ⚠️ May 8, 2026
85% Committed - In Delivery
Milestone 4 complete and about to go to QA
Streamline Envs & Dev Cycle Process
Josh - Overdue
100% Committed - Done
Work completed and last little bit with QA
Hangfire → Message Queue
Simon - TBD
100% Committed - QA
QA resource dependent. Released next week behind a feature flag. Will go live week after Easter
US Infra & Environments Runbook
Julien, Faisal, Josh - ASAP
100% Committed - QA
Complete but QA and Infra doing back and forth and making performance tweaks
Localisation – Timestamps AUD→US
Van, Adi - May 2026
70% Provisional - In Delivery
FE and BE are working through tickets. BE is a little more work than the FE side
Square SDK Security – Digital Signature
Jack, Diet, FE-TBC - Apr–Jun 2026
100% Committed - QA
Completed - with QA.
Gift Card UI/UX + No Expiry (USA/CA)
Yunfang, FE team - May 2026
90% Committed - In Delivery
Dev completion due 27 Mar. Priority 1 = No expiry for USA/CA. Priority 2 = UI/UX widget redesign.
CRM/EDM Integration – iframe partner
TBC - May 2026
100% Committed - Done
Done - P1 subscription button in admin complete. P2 (NBI domain) and P3 (SSO) post-launch.
Google Book Now Integration
Simon - May 2026 (conditional)
70% Provisional - In Delivery
Merchant Feed ~ready 13 Mar. Service Feed ~ready 20 Mar. Availability Feed ~ready 8 Apr (most complex). Booking Service and RTUs from 9 Apr, aiming to finish 24 Apr. Slow feedback cycle (24hr+ per test).
MOBILE APP MVP MILESTONES
M1 - Header, Dates, Service, Time, Search
Closed
M2 - Booking Card List & Filters
Closed
M3 - Booking Form Wizard
Dev: Mar 2-27 - QA: Mar 30-Apr 3
M4 - Manage Bookings
Complete - going to QA
M5 - Floor Plan MVP
Dev: Apr 25-May 1 - QA: May 4-7
M6 - Launch - Hard deadline
May 8, 2026

Shipped and Near-Done

COMPLETED / NEAR-DONE
BI/AI Reporting Dashboard
Dietloff, Adi
UAT → Pilot
Reservations API – Signature Group MVP
GG
QA Complete
Streamline Envs & Dev Cycle Process
Josh
Done
CRM/EDM Integration – iframe partner
TBC
Done
scroll to zoom - drag to pan - hover nodes for details