Now Book It
Indicative 0–40%
Provisional 41–70%
Committed 71–100%
NOW
NEXT
LATER

πŸ“… Current Sprint β€” Q1 2026

Active Delivery
BI/AI Reporting Dashboard
Dietloff, Adi
🟒 100% Β· UAT β†’ Pilot
Reservations API – Signature Group MVP
GG Β· Target Feb 13, 2026
🟒 80% · QA Complete
Bookings Past Midnight
Adi, Van, Luwan Β· Overdue from Nov 2025
🟑 51% · In QA
Stage 1 – Adyen/ValPay
Hina Β· Target Mar 18, 2026
🟒 100% · In Delivery
Floor Plan & Mobile – Native App MVP
Philip, Luwan, Jim · ⚠️ May 8 Hard Deadline
🟒 100% · In Delivery
Streamline Envs & Dev Cycle Process
Josh Β· Overdue
🟑 51% · In Delivery
Hangfire Abuse β†’ Message Queue
Simon Β· TBD – pending Jack input
πŸ”΄ TBD Β· In Delivery
Mobile App MVP Milestones
M1 – Header, Dates, Service, Time, Search
Dev: Now–Feb 13 Β· QA: Feb 16–17 Β· Bugs: Feb 18–20
⚠️ Vietnamese QA away Feb 16–20
M2 – Booking Card List & Filters
Dev: Feb 16–27 Β· QA: Mar 2–6 Β· UAT: Mar 16–20
M3 – Booking Form Wizard
Dev: Mar 2–27 Β· QA: Mar 30–Apr 3 Β· UAT: combined M4
M4 – Manage Bookings
Dev: Mar 30–Apr 17 Β· QA: Apr 20–24 Β· UAT: Apr 27–May 1
M5 – Floor Plan MVP
Dev: Apr 20–May 1 Β· QA: May 4–7
M6 – Launch ⚠️
May 8, 2026 Β· Hard deadline
Refinement Checkpoints
w/c 23 Feb Β· Infra/Env Scoping
Julien & Faisal confirm US env timeline β€” unblocks all NEXT items
w/c 2 Mar Β· Dev Estimation Sessions
All NEXT items scoped β€” bands move πŸ”΄ β†’ 🟑 minimum
w/c 9 Mar Β· Roadmap v2 Published
Updated dates with month-level precision
w/c 23 Mar Β· Mid-Point Check
All committed items at 🟒 · Risks escalated
w/c 27 Apr Β· Pre-Launch Gate Review
USA readiness checklist Β· confirm or descope
End of May 2026 · USA Launch 🎯
All committed USA readiness items live

πŸ“¦ Recently Shipped & In Flight

UAT / Pilot
BI/AI Reporting Dashboard
Dietloff, Adi Β· Entering Pilot now
UAT β†’ Pilot
QA Complete
Reservations API – Signature Group MVP
GG Β· Feb 13, 2026
QA Complete
In QA
Bookings Past Midnight
Adi, Van, Luwan Β· Originally Nov 2025 target
In QA
Immediate Next Steps
Julien & Faisal
Confirm US infra/env timeline by w/c 23 Feb β€” critical path, unblocks multiple streams
Jem
Schedule eng estimation sessions for all NEXT items β€” w/c 2 March
Philip / Jim
Align on design for Mobile App + Floor Plan Web App β€” shared design session to book
Jem / Tim / Pete
Complete GC UI/UX scoping brief before FE can be assigned
scroll to zoom Β· drag to pan Β· hover nodes for details