BI/AI Reporting Dashboard
Dietloff, Adi - UAT → Pilot
100% Committed - UAT → PilotPilot is going well, getting more data as we now have 31 venues in the pilot. Some bug fixes and updates have been made based on feedback.
Reservations API – Signature Group MVP
GG - Feb 13, 2026
100% Committed - QA CompleteCompleted - MVP rolled out for Signature Group. In testing with Dev. Will be tested when QA is available.
Stage 1 – Adyen / ValPay
Hina - Mar 18, 2026
90% Committed - In DeliveryIn Delivery - completing tech debt component before parking ValPay build. Estimated completion 10 Apr.
Floor Plan & Mobile – Native App MVP
Philip, Luwan, Jim - ⚠️ May 8, 2026
85% Committed - In DeliveryMilestone 4 complete and about to go to QA
Streamline Envs & Dev Cycle Process
Josh - Overdue
100% Committed - DoneWork completed and last little bit with QA
Hangfire → Message Queue
Simon - TBD
100% Committed - QAQA resource dependent. Released next week behind a feature flag. Will go live week after Easter
US Infra & Environments Runbook
Julien, Faisal, Josh - ASAP
100% Committed - QAComplete but QA and Infra doing back and forth and making performance tweaks
Localisation – Timestamps AUD→US
Van, Adi - May 2026
70% Provisional - In DeliveryFE and BE are working through tickets. BE is a little more work than the FE side
Square SDK Security – Digital Signature
Jack, Diet, FE-TBC - Apr–Jun 2026
100% Committed - QACompleted - with QA.
Gift Card UI/UX + No Expiry (USA/CA)
Yunfang, FE team - May 2026
90% Committed - In DeliveryDev completion due 27 Mar. Priority 1 = No expiry for USA/CA. Priority 2 = UI/UX widget redesign.
CRM/EDM Integration – iframe partner
TBC - May 2026
100% Committed - DoneDone - P1 subscription button in admin complete. P2 (NBI domain) and P3 (SSO) post-launch.
Google Book Now Integration
Simon - May 2026 (conditional)
70% Provisional - In DeliveryMerchant Feed ~ready 13 Mar. Service Feed ~ready 20 Mar. Availability Feed ~ready 8 Apr (most complex). Booking Service and RTUs from 9 Apr, aiming to finish 24 Apr. Slow feedback cycle (24hr+ per test).
MOBILE APP MVP MILESTONES
M1 - Header, Dates, Service, Time, Search
Closed
M2 - Booking Card List & Filters
Closed
M3 - Booking Form Wizard
Dev: Mar 2-27 - QA: Mar 30-Apr 3
M4 - Manage Bookings
Complete - going to QA
M5 - Floor Plan MVP
Dev: Apr 25-May 1 - QA: May 4-7
M6 - Launch - Hard deadline
May 8, 2026